| Client | Project Name | Product | Q'ty | Weight (Ton) | 
|---|---|---|---|---|
| Total | CLOV FPSO | Hull Part Pipe Rack | 7 Blocks | 1,821 | 
| Topside Pipe Rack | 3 Modules | 1,902 | ||
| I-Tube | 10 Blocks | 1,054 | ||
| Cassion | 9 Blocks | 351 | ||
| Exxon Mobil | Arkutun Dagi Fixed Platform  | 
                    Flare Boom | 1 EA | 235 | 
| Chevron | SNX Fixed Platform  | 
                    Bridge | 1 EA | 226 | 
| Cooler Deck | 2 P.E | 393 | ||
| Helideck | 1 EA | 135 | ||
| Chevron | Wheatstone Fixed Platform  | 
                    Intermediate Deck | 2 P.E | 589 | 
| Upper Deck | 1 P.E | 370 | ||
| Vertical Frame | 4 Blocks | 500 | ||
| IUK | Angola Panel yard | 2,500 Ton Heavy Lift Crane | 1 EA | 3,500 | 
| Dong Energy | Dong Hejre Field Fixed Platform  | 
                    Cellar Deck | 1 P.E | 641 | 
| Intermediate Deck | 1 P.E | 445 | ||
| Acess Way Deck | 1 P.E | 21 | ||
| Lower Deck | 1 P.E | 27 | ||
| Platform | 4 Blocks | 60 | ||
| Grillage Beam | 10 Blocks | 3,044 | ||
| Petronas | Petronas FLNG  | 
                    Process Deck | 6 Blocks | 874 | 
| Mezz. Deck | 2 P.E | 137 | ||
| Upper Deck | 3 P.E | 828 | ||
| Top Deck | 1 P.E | 181 | ||
| Platform | 2 Blocks | 129 | ||
| Topside Pipe Rack | 2 Modules | 204 |